This is the list of the MPO's ongoing transportation studies. The list includes title, description, schedule, cost, consultant, and project manager. We also provide progress status for ongoing studies.

*Status information provided below as of September 30, 2015.

  • 2040 Regional Transportation Plan 2013

    This plan provides a prioritized set of highway and transit improvements for Miami-Dade, Broward, and Palm Beach counties recognizing the regional characteristics of many travel needs. Miami-Dade's share is $150,000 with remaining amount being provided in equal parts by the Broward and Palm Beach MPOs.

    STATUS: 98% complete

     

    • Work by Kittleson and Associates
    • Budgeted amount is $900,000
    • Managed by Wilson Fernandez
  • Bicycle and Pedestrian Traffic Count Program 2014

    Develop a program for collecting bicycle and pedestrian counts at significant roads, trails, and transit locations. This will update the study titled Bicycle and Pedestrian Traffic County Program 2006.

    STATUS: 98% complete

     

    • Work by Kimley-Horn & Associates
    • Budgeted amount is $50,000
    • Managed by David Henderson
  • Bike Friendly Miami-Dade Plan 2015

    A description of this study is forthcoming.

    STATUS: Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $120,000
    • Managed by David Henderson
  • City of Miami Little Havana Bicycle/Pedestrian Mobility Study 2015

    Prepares a bicycle/pedestrian mobility plan for the Little Havana Neighborhoods.

    STATUS: 25% complete

     

    • Work by City of Miami
    • Budgeted amount is $40,000
    • Managed by David Henderson
  • Countywide Bicycle/Pedestrian Plan 2013

    Create a non-motorized section of the 2040 Long Range Transportation Plan including proposed projects and programs to increase the number of people who walk or ride a bicycle while reducing the number of injuries and fatalities.

    STATUS: 100% complete

     

    • Work by Kimley-Horn & Associates
    • Budgeted amount is $100,000
    • Managed by David Henderson
  • Evaluating Feasibility of Superarterials 2015

    A description of this study is forthcoming.

    STATUS: Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $120,000
    • Managed by Wilson Fernandez
  • Federal Planning Emphasis Areas for Miami-Dade County 2015

    A description of this study is forthcoming.

    STATUS:  Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $75,000
    • Managed by Carlos Roa
  • Impact of PortMiami Tunnel on Downtown Traffic Congestion 2014

    Identify congestion caused by private and commercial vehicular traffic and freight traffic along with transit congestion points since the opening of the PortMiami Tunnel. The reduction in truck traffic due to the tunnel opening will be temporary as it is anticipated that Port growth will result in levels as high as those prior to the tunnel opening by the year 2035. A multi-modal congestion evaluation of downtown Miami is a critical element to plan for in order to maintain mobility.

    STATUS: 70% complete

     

    • Work by Kimley-Horn & Associates
    • Budgeted amount is $130,000
    • Managed by Carlos Roa
  • LeJeune Road at SW 8th Street Intersection Study 2014

    Evaluate the operating conditions of the intersection and identify improvement concepts.  The analysis will evaluate safety, along with operational and multimodal improvements. Alternative intersection designs and concepts, intersection widening, movement restrictions, and traffic diversion affecting adjacent neighborhoods, will also be evaluated. In 2005, the MPO evaluated a grade separation concept (overpass) for this location, but it was deemed unsuitable for implementation at the time.

    STATUS: 98% complete

     

    • Work by Jacobs Engineering
    • Budgeted amount is $125,000
    • Managed by Carlos Roa
  • Miami River Tunnel Feasibility 2015

    A description of this study is forthcoming.

    STATUS: Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $200,000
    • Managed by Carlos Roa
  • Online Walk to School Planner Phase II 2013

    Develop a version of the Walk to School Route Planner web application that is optimized for mobile devices and smartphones.

    STATUS: 50% complete

     

    • Work by Florida International University; University of Florida
    • Budgeted amount is $100,000
    • Managed by David Henderson
  • Opa-Locka Transportation Master Plan and Enhancements Study Phase I 2012

    A description of this study is forthcoming.

    STATUS: 100% complete (Awaiting final documents)

     

    • Work by City of Opa-Locka
    • Budgeted amount is $54,304
    • Managed by Wilson Fernandez
  • Optimizing Transit Revenue and Capacity 2015

    A description for this study is forthcoming.

    STATUS: Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $130,000
    • Managed by Wilson Fernandez
  • South Florida Clean Energy and Greenhouse Gas Emission Reduction Program 2009

    It will accelerate the growth and development of alternative fuel fleets, fuel suppliers and awareness in the four county regions.

    STATUS: 100% complete (Awaiting final documents)

     

    • Work by South Florida Regional Planning Council (SFRPC)
    • Budgeted amount is $50,000
    • Managed by Susan Schreiber
  • SW 8th Street Corridor 2013

    Determine and document the need for corridor improvements and develop alternative solutions to alleviate traffic flow along SW 8th Street between 74th Avenue and 122nd Avenue.

    STATUS: 90% complete

     

    • Work by HNTB
    • Budgeted amount is $297,400
    • Managed by Carlos Roa
  • Transportation Planning Process: Development of Computerized Techniques 2012

    Develop high-tech computerized strategies detailing the importance and benefits of the different transportation projects and how they will improve the transportation system in Miami-Dade County.

    STATUS: 85% complete

     

    • Work by Kimley-Horn & Associates
    • Budgeted amount is $175,000
    • Managed by Jesus Guerra
  • Travel Household Survey 2014

    To gather travel data that is valuable in understanding travel behavior in Southeast Florida region and lead to the development and improvement of transportation planning tools used to assess future projects and policies.

    STATUS: 5% complete

     

    • Work by Parsons Brinckerhoff
    • Budgeted amount is $1,500,000
    • Managed by Wilson Fernandez
  • Visualization Tool of Traffic Flow 2015

    A description of this study is forthcoming.

    STATUS: Pending execution of GPC VI

     

    • Work by [To be determined]
    • Budgeted amount is $150,000
    • Managed by Carlos Roa
Back to Top Page Last Edited: Fri Mar 3, 2017 8:04:43 AM
 
 
Corner
  • Facebook Twitter YouTube RSS SlideShare Instagram SMS
  • Print Print Email this page Email Page   | Bookmark and Share
  • Minimize Tools
Corner

You are now leaving the official website of Miami-Dade County government. Please be aware that when you exit this site, you are no longer protected by our privacy or security policies. Miami-Dade County is not responsible for the content provided on linked sites. The provision of links to these external sites does not constitute an endorsement.

Please click 'OK' to be sent to the new site, or Click 'Cancel' to go back.